Most bathroom renovation delays come from a short list: materials that aren't on site, decisions that change mid-job, trades that aren't lined up, hidden problems behind the walls, and, for tiled showers, inspection bookings. Almost all of them can be prevented before the first day on site.
Here's what causes each one and what we do about it, so your bathroom finishes on the date we give you.
1. Materials that aren't there when they're needed
A vanity on back order or a tile that's run out can stop a job for days, because the next trade can't start. It's the most common bathroom renovation delay we see on jobs other people started.
How we avoid it: your fittings and finishes are chosen and ordered before the start date, and we confirm they're in stock or on hand. Our packages use set scopes, which keeps ordering simple.
2. Decisions that change part-way through
Changing the tile after the waterproofing is done, or swapping a floor-standing vanity for a wall-hung one after the walls are lined, means new orders and rework. It's completely understandable, but it costs time.
How we avoid it: we settle the scope in writing before work starts. If you do want a change, we price it and tell you the effect on the finish date before going ahead. The 3D bathroom designer helps you see the room before committing.
3. Trades that aren't lined up
When you hire a plumber, electrician and tiler separately, each one fits your job around their other bookings. A one-day gap between each stage soon adds up to a week.
How we avoid it: one team runs the whole job and books every trade into a fixed programme. We compare the two approaches in one company or separate trades?

4. Hidden problems behind the walls
Rot under an old shower, borer, tired wiring or a sagging floor won't show until the walls and floor are open. In older Auckland villas and bungalows, it's common.
How we avoid it: our pre-start check catches most of it, so it's in the price and the programme from the start. If something hidden still turns up, we stop, show you, and price the fix separately before carrying on. Nothing changes without you knowing. See hidden costs in a bathroom renovation.
5. Consent and inspections
A tiled shower needs building consent in Auckland, with inspections during the build. If consent is lodged late, or inspections aren't booked ahead, the job waits.
How we avoid it: for our Full Tile package we lodge the consent before work starts and plan the programme around inspection bookings. You can see where each inspection falls in a fully tiled bathroom, week by week. For the bigger picture on consent, read do you need building consent for a bathroom renovation?
Fixed price · fixed finish date
Indicative starting prices. Your fixed price is confirmed after a short site check.
Not sure which one? Plan it free in 3D or get an instant estimate.
6. Holidays and the time of year
The Christmas and New Year shutdown slows suppliers and council. Damp winter weather can also slow drying of membranes and adhesives. We cover how to plan around it in the best time of year to renovate a bathroom.
What a realistic programme looks like
Our packages take about 1, 2, 3 or 4 weeks on site, depending on the scope. That time is fixed in writing before we start. Read our guide to how long a bathroom renovation takes for what's included in each.
Frequently asked questions
What causes bathroom renovation delays?
The most common causes are materials not on site, changes to the scope part-way through, trades with gaps between bookings, hidden problems such as rot, and, for tiled showers, consent and inspection timing.
How do I stop my bathroom renovation running late?
Make every choice before the start date, order early, use one company that runs all the trades on a fixed programme, and get a written finish date. Ask what happens if something hidden turns up.
What happens if you find rot?
We stop, show you, and price the fix separately before carrying on. The pre-start check finds most of it, so surprises are rare, but you'll always know before anything changes.
Does council slow down a bathroom renovation?
Only for consented work, such as a tiled shower. Lodging consent before work starts and booking inspections ahead keeps it from holding up the job.