A fully tiled bathroom renovation follows the same bathroom renovation steps every time: strip-out, framing, plumbing and electrical rough-in, a pre-line inspection, wall linings, waterproofing and its inspection, tiling, fit-off and a final inspection. For our Full Tile package that takes about four weeks on site.
Here's roughly how those four weeks fall. Every bathroom is a bit different, and inspection bookings and what we find behind the walls can shift things by a day or two, so treat this as a typical order of work rather than a fixed timetable.
Before week 1: consent and ordering
A tiled shower needs building consent in Auckland, so we prepare and lodge it before anything happens on site. How long council takes depends on council, which is why we set the start date around it. We explain why in why a tiled shower needs building consent.
While that's in progress you choose your tiles, vanity, tapware and toilet, and we order them so they're on hand when each trade needs them.
Week 1: strip-out and rough-in
Strip-out
The old bathroom comes out: fittings, tiles or linings, and often the floor covering. Dust protection goes up first, and the rubbish goes straight out to a skip or trailer. This is the noisiest part of the job.
Framing check and repairs
With the walls open we can see the framing. This is where rot under an old shower, borer or a sagging floor shows up. Most of it is picked up at the pre-start check, but if something hidden turns up, we stop, show you, and price the fix separately before carrying on. Read more in hidden costs in a bathroom renovation.
Any new framing for niches, a wall-hung vanity, grab rails or the shower goes in now.
Plumbing and electrical rough-in
The plumber runs new supply and waste pipes to the fitting positions. The electrician wires lights, the extractor fan, a heated towel rail and any mirror lighting. These are the parts you'll never see again, so they're done before anything is closed in.
Week 2: inspection, linings and waterproofing
Pre-line inspection
Before the walls are lined, council inspects the framing and rough-in. We book this in advance, but the exact day depends on council's availability.
Lining
Once it passes, the walls and shower area are lined with a wet-area board, and the shower floor is prepared with the right fall to the waste.
Membrane and inspection
The waterproofing membrane goes on, lapped into the waste and up the walls. It needs time to cure, and then council usually inspects it before any tile covers it. This is the most important stage of the whole job, because the membrane, not the tile, is what keeps water out of the frame. See bathroom waterproofing and the Building Code.

Week 3: tiling
The tiler sets out the walls and floor so cuts land in sensible places, then lays the tiles, forms any niches, and grouts. Large-format tiles and patterned or small tiles take longer than plain ones. Adhesive and grout need time to set before the shower can be used.
Fixed price · fixed finish date
Indicative starting prices. Your fixed price is confirmed after a short site check.
Not sure which one? Plan it free in 3D or get an instant estimate.
Week 4: fit-off and final inspection
Fit-off
The vanity, toilet, tapware, shower glass, towel rail, mirror and lights go in. The plumber and electrician connect everything, silicone is run, and the room is cleaned.
Final inspection
Council does a final inspection. After that, and once the paperwork is in, council issues the Code Compliance Certificate. The certificate itself can come through after you're already using the bathroom. We explain it in Code Compliance Certificates, explained.
How this compares to the shorter packages
The Refresh, Upgrade and Tile-Look skip most of these steps. There's no consent, no on-site membrane and no grout to cure, so the time on site drops to one, two or three weeks. Our guide to how long a bathroom renovation takes sets out all four side by side, and what delays bathroom renovations covers what can stretch any of them.
Frequently asked questions
What are the steps in a bathroom renovation?
For a fully tiled bathroom: strip-out, framing repairs, plumbing and electrical rough-in, a council pre-line inspection, wall linings, the waterproofing membrane and its inspection, tiling and grouting, fit-off, and a final inspection before the Code Compliance Certificate.
How long does each stage take?
In our Full Tile package, roughly a week each for strip-out and rough-in, inspection and waterproofing, tiling, and fit-off. Inspection bookings and anything found behind the walls can move a stage by a day or two.
Can I use the bathroom during the renovation?
No. From strip-out to fit-off the room isn't usable. If it's your only bathroom, see our guide to renovating your only bathroom.
When do the council inspections happen?
Usually before the walls are lined, again when the membrane is down and before tiling, and at the end for the final inspection. The exact days depend on council's booking availability.