Timelines & living through it

A fully tiled bathroom renovation, week by week

The order of work in a fully tiled bathroom renovation: strip-out, framing, plumbing, waterproofing, tiling and fit-off, week by week.

By the Weekly Bathrooms team · backed by Add Value Renovations, Registered Master Builder · 10 November 2026 · 4 min read

Large-format marble-look tiles, freestanding bath and frameless glass shower in a Blockhouse Bay bathroom
Large-format marble-look tiles, freestanding bath and frameless glass shower in a Blockhouse Bay bathroom · Blockhouse Bay renovation by Add Value Renovations

A fully tiled bathroom renovation follows the same bathroom renovation steps every time: strip-out, framing, plumbing and electrical rough-in, a pre-line inspection, wall linings, waterproofing and its inspection, tiling, fit-off and a final inspection. For our Full Tile package that takes about four weeks on site.

Here's roughly how those four weeks fall. Every bathroom is a bit different, and inspection bookings and what we find behind the walls can shift things by a day or two, so treat this as a typical order of work rather than a fixed timetable.

A tiled shower needs building consent in Auckland, so we prepare and lodge it before anything happens on site. How long council takes depends on council, which is why we set the start date around it. We explain why in why a tiled shower needs building consent.

While that's in progress you choose your tiles, vanity, tapware and toilet, and we order them so they're on hand when each trade needs them.

Week 1: strip-out and rough-in

Strip-out

The old bathroom comes out: fittings, tiles or linings, and often the floor covering. Dust protection goes up first, and the rubbish goes straight out to a skip or trailer. This is the noisiest part of the job.

Framing check and repairs

With the walls open we can see the framing. This is where rot under an old shower, borer or a sagging floor shows up. Most of it is picked up at the pre-start check, but if something hidden turns up, we stop, show you, and price the fix separately before carrying on. Read more in hidden costs in a bathroom renovation.

Any new framing for niches, a wall-hung vanity, grab rails or the shower goes in now.

Plumbing and electrical rough-in

The plumber runs new supply and waste pipes to the fitting positions. The electrician wires lights, the extractor fan, a heated towel rail and any mirror lighting. These are the parts you'll never see again, so they're done before anything is closed in.

Week 2: inspection, linings and waterproofing

Pre-line inspection

Before the walls are lined, council inspects the framing and rough-in. We book this in advance, but the exact day depends on council's availability.

Lining

Once it passes, the walls and shower area are lined with a wet-area board, and the shower floor is prepared with the right fall to the waste.

Membrane and inspection

The waterproofing membrane goes on, lapped into the waste and up the walls. It needs time to cure, and then council usually inspects it before any tile covers it. This is the most important stage of the whole job, because the membrane, not the tile, is what keeps water out of the frame. See bathroom waterproofing and the Building Code.

Tiled walk-in shower, bath behind glass, timber-look vanity and lit wall niche in a Lynfield bathroom
A tiled walk-in shower with a lit wall niche: every tile here sits over a membrane that was inspected first. · Lynfield renovation by Add Value Renovations

Week 3: tiling

The tiler sets out the walls and floor so cuts land in sensible places, then lays the tiles, forms any niches, and grouts. Large-format tiles and patterned or small tiles take longer than plain ones. Adhesive and grout need time to set before the shower can be used.

Fixed price · fixed finish date

Indicative starting prices. Your fixed price is confirmed after a short site check.

Not sure which one? Plan it free in 3D or get an instant estimate.

Week 4: fit-off and final inspection

Fit-off

The vanity, toilet, tapware, shower glass, towel rail, mirror and lights go in. The plumber and electrician connect everything, silicone is run, and the room is cleaned.

Final inspection

Council does a final inspection. After that, and once the paperwork is in, council issues the Code Compliance Certificate. The certificate itself can come through after you're already using the bathroom. We explain it in Code Compliance Certificates, explained.

How this compares to the shorter packages

The Refresh, Upgrade and Tile-Look skip most of these steps. There's no consent, no on-site membrane and no grout to cure, so the time on site drops to one, two or three weeks. Our guide to how long a bathroom renovation takes sets out all four side by side, and what delays bathroom renovations covers what can stretch any of them.

Frequently asked questions

What are the steps in a bathroom renovation?

For a fully tiled bathroom: strip-out, framing repairs, plumbing and electrical rough-in, a council pre-line inspection, wall linings, the waterproofing membrane and its inspection, tiling and grouting, fit-off, and a final inspection before the Code Compliance Certificate.

How long does each stage take?

In our Full Tile package, roughly a week each for strip-out and rough-in, inspection and waterproofing, tiling, and fit-off. Inspection bookings and anything found behind the walls can move a stage by a day or two.

Can I use the bathroom during the renovation?

No. From strip-out to fit-off the room isn't usable. If it's your only bathroom, see our guide to renovating your only bathroom.

When do the council inspections happen?

Usually before the walls are lined, again when the membrane is down and before tiling, and at the end for the final inspection. The exact days depend on council's booking availability.

Free · no obligation

Plan it in 3D. Price it in 2 minutes.

Plan your bathroom in 3D, get your starting price in two minutes, or do both. They work side by side.

Which week is your bathroom?

Call us for a fixed price and a finish date in writing.